Missing or unverified documents can put an Islington licence application at risk of rejection. Fees are non-refundable; Part A is not returned if an application is refused, withdrawn, or rejected for fraudulent or incorrect details. Discounts can also be lost if an application is late, the council has issued a formal warning, or it makes two or more requests for missing or corrected documents. Here is every safety certificate you need — and the validity window the council checks.
Electrical Installation Condition Report (EICR)
Every property licence application in Islington — mandatory HMO, additional HMO, selective or Section 257 — requires a valid EICR. The report must be no more than five years old at the time of submission and show a "Satisfactory" overall result. If it flags C1 (danger present) or C2 (potentially dangerous) defects, they must be rectified. Follow the portal's instructions for evidence of remedial work.
The EICR must be carried out by a qualified electrician. Keep the original report and evidence of any remedial work; the council may request it during a compliance inspection.
Gas Safety Certificate (CP12)
If the property has any gas appliances — boiler, hob, fire — you need a Gas Safe registered engineer's certificate dated within the last 12 months. The certificate must cover every gas appliance and flue in the property, not just the boiler.
Once the licence is granted, the gas safety certificate becomes a rolling annual obligation. You must submit a new CP12 to the council every year for the duration of the licence. Missing one annual renewal is a licence condition breach that can trigger a civil penalty of up to £40,000.
Energy Performance Certificate (EPC)
The property needs a valid EPC — maximum 10 years old — rated at least Band E. If the EPC has expired or shows Band F or G, the property cannot be legally let under the Minimum Energy Efficiency Standards (MEES) regulations unless you have registered a valid exemption on the PRS Exemptions Register.
Islington also offers a £50 discount on the Part B licence fee for properties with an EPC rating of A, B or C. If you have recently upgraded the property's insulation or heating, getting a fresh EPC before you apply could save you money on the licence itself.
Free Download
Get the Islington Landlord Licensing Checklist
Everything in this article as a printable checklist — plus action plans and reference guides you can start using today.
Fire Risk Assessment (FRA)
Where required for a mandatory or additional HMO, the application needs a written fire risk assessment. The FRA should be reviewed annually and evaluate structural fire protection and alarm systems.
For HMOs with installed Grade A or BS 5839-compliant fire detection systems, Islington also requires annual commissioning and testing certificates from a qualified fire alarm engineer. These are separate from the FRA itself.
Selective licence properties (single-household lets) do not require a formal FRA, but smoke and carbon monoxide alarms are still mandatory.
Smoke and Carbon Monoxide Alarms
Every property that requires an Islington licence must have working smoke alarms on every storey used as living accommodation. Carbon monoxide detectors are required in any room containing a gas appliance or a solid fuel burning appliance (wood burner, open fire).
For HMOs, additional fire-alarm conditions may apply. Check the conditions for the specific scheme and property; do not assume the same alarm configuration applies to every HMO.
Keeping Certificates Current After the Licence Is Granted
Getting the initial certificates right is only half the job. Once your five-year licence is active, Islington's licence conditions require you to maintain every certificate within its validity period and submit updated copies to the council when requested. The annual gas safety certificate is the most frequent obligation, but EICR renewals (every five years) and FRA reviews (annually for HMOs) will also fall due during a standard licence term.
A compliance tracker that logs certificate dates, next renewal deadlines and inspection outcomes makes the difference between a smooth mid-licence inspection and a civil penalty notice. Our Islington Landlord Licensing Guide includes a five-year condition maintenance tracker and a pre-application document checklist that maps every certificate to the council's upload requirements — so nothing is missing when you hit submit.
Get Your Free Islington Landlord Licensing Checklist
Download the Islington Landlord Licensing Checklist — a printable guide with checklists, scripts, and action plans you can start using today.